Paving Schedule-Road Closures/Delays


The Township is currently in the second phase of Paving and Road applications.  As of 8/24/17, the schedule is as follows:

**Greenwood Road is scheduled to receive an Oil and Chip application during the week of August 28th. This is a one day job, the road will be closed during this work, detours will be posted.
**The Hartefeld development will be paved the week of 8/30/17 thru 9/5/17.
**Bainswood Drive and Bainswood Circle is scheduled for paving 9/6/17 thru 9/8/17.

Dates are weather dependent.  Bad weather will push work out further.

Please refrain from blowing grass onto these roadways during this period. No on street parking can take place at this time.

We thank you for your patience and attention to the posted signs and directions during this work.